Scarboro Community Development
104 New Doors Opening in 2026–2027
We are hard at work building high-quality, affordable homes for our community. This project features four buildings designed for families and seniors, providing safe and stable housing for over 100 households.
Preparing the Foundation
Phase 1: Setting the Stage
Before we build up, we have to prepare the ground. From December 2025 through May 2026, our teams are:
Clearing the site and leveling the land.
Installing essential underground water, power, and sewer lines.
Preparing the roads and curbs for future residents.
Rising Above the Ground
Phase 2: Foundations & Framework
Starting in the Spring of 2026, you will see the site transform quickly. We are using a "rolling" schedule to keep construction moving efficiently:
April – July 2026: Foundations and concrete slabs are poured for all four buildings.
May – September 2026: The exterior "shells" of Buildings 1 and 2 take shape.
A New Neighborhood Takes Shape
Phase 3: Finishing the Vision
As the exteriors wrap up, our focus moves inside to turn these structures into homes.
Building 1 (26 Units): Completing November 2026.
Building 2 (24 Units): Completing December 2026.
Buildings 4 & 6 (54 Units): These larger buildings will see intensive interior work through the Winter, heading toward a Spring/Summer 2027 finish.
The Finish Line
Projected Completion: June 2027
We are on track to welcome our final residents in early Summer 2027. This project is more than just sticks and bricks — it's the foundation for a stronger, more affordable East Tennessee.
Interactive Impact Counter
104 Units of Housing
20 Months of Construction
4 Modern Buildings
1 Stronger Community